Riverwalk work on pace for fall finish

AUBURN - Crews are on pace to finish building a bike path and underpass along the Androscoggin River downtown by the fall, despite the past few weeks' rainy weather.

jleiva

Jose Leiva/Sun Journal

Work on the Riverwalk underpass on the Auburn side of Longley Bridge continues Thursday.

"I think all the rain did slow us down, but we had a few extra days built in at the beginning," said Eric Labelle, Auburn's community services director.

Workers are digging the path and a retaining wall out of the bank of the river behind TD Banknorth at Great Falls Plaza. That includes installing footers and the foundation for the path and the wall.

"You can get a real sense of what it's going to look like now, with the structure going in," Labelle said. "The next step will be pouring the concrete. Once we do that, things will move along really quickly."

When it's finished in November, the path will extend under the bridge, connecting Great Falls Plaza, the Hilton Garden Inn and West Pitch Park to the city's Riverwalk.

Officials have been planning the underpass for a number of years.

The city extended the Riverwalk path from Festival Plaza to the southern edge of Court Street in July 2006. That involved building a new path along the river behind Gritty McDuff's brew pub and a flat landing directly beneath Longley Bridge.

A stairway connecting Court Street to the Riverwalk below opened in summer 2007. That lets pedestrians continue walking along the river without having to detour up Main Street, but it doesn't go under Court Street.

The city received a $600,000 grant from the state's current budget to build the underpass, but bids came in $45,000 higher. The state agreed in May to give the additional $45,000 to complete the project.

staylor@sunjournal.com

Stay informed — Get the news delivered for free in your inbox.

I'm interested in ...

In order to make comments, you must verify your account.

In order to comment on SunJournal.com, you must use your real name and include the town in which you live in your profile. A member of our staff will call you to verify this information. To join in, fill out your user profile completely and check the box "please verify my status." We'll get back to you within one business day to verify your account.

Login or create an account here.

Our policy prohibits comments that are:

  • Defamatory, abusive, obscene, racist, or otherwise hateful
  • Excessively foul and/or vulgar
  • Inappropriately sexual
  • Baseless personal attacks or otherwise threatening
  • Contain illegal material, or material that infringes on the rights of others
  • Commercial postings attempting to sell a product/item
If you violate this policy, your comment will be removed and your account may be banned.

Advertisement

Displaying comments, from newest to oldest

wen's picture

jjjjj

jjjjj

wheelie207's picture
verified

I was told by one of the

I was told by one of the workers doing the concrete wall that the end of the riverwalk was going to be very steep and didn't think that wheelchairs would make it.
I myself think the walk should be elevaated enough for those in wheelchairs to use it as well as those that can walk.
I hope I can get the city to fix the end of the walk not so steep and to make it enough for wheelchairs to use it too.

Advertisement