BRUNSWICK — The proposed seasonal weekend Downeaster service to the Midcoast has been delayed yet again and won’t be ready for summer operation, said Patricia Quinn, executive director of the Northern New England Passenger Rail Authority.

The Coastal Connection would run two-hour weekend trips from Brunswick to Rockland with stops in Bath, Wiscasset and Newcastle.

The Northern New England Passenger Rail Authority manages Maine’s contract with Amtrak, but the Maine Department of Transportation owns the 58-mile track between Brunswick and Rockland and leases it to the Central Maine and Quebec Railway to carry freight, Quinn said. Because of this, there are many moving pieces that need to be sorted out in order to start training crews to run the service.

“It’s taking longer than anticipated for the legal operating requirements side,” she said, adding that they will “continue the dialogue.”

The rail service planned to offer a three-week run in summer 2018 during the Maine Lobster Festival and the Maine Boats, Homes & Harbors show in August, but that was canceled because the rail authority could not complete a safety assessment of the track between Brunswick and Rockland in time. Amtrak must make sure the track is able to handle the speeds of passenger trains.

The safety assessment is one of the pieces in play, Quinn said, adding that is in progress.

Advertisement

There has been “very strong interest from the (Midcoast) community,” she said, as the line is partly intended to help boost tourism. Community members “see the potential as much, if not more than we do,” Quinn said.

“The Midcoast is very popular in the summer and Route 1 gets very congested,” she added, making train service a good fit.

“The railroad is there, it’s in good shape and we have the availability of the equipment on the weekends,” Quinn said.

Passenger service has not operated on the Brunswick-to-Rockland line since the Maine Eastern Railroad shut down in 2015, the rail authority said.

Originally, it was estimated that the service would cost $200,000 and transport approximately 7,000 riders, generating approximately $120,000 in revenue. The authority will have to take a second look at the cost after details are ironed out, but the service is “not a millions of dollars kind of thing,” Quinn said.

In February 2018, David Bernhardt, then-commissioner of the Department of Transportation, said in a letter to the rail authority that the DOT would “not support financially the proposed service and will not approve use of additional state or federal funds for this purpose.”

Advertisement

The conclusion that the rail corridor was in good shape was lacking in some facts, the letter said, as “in the past two years the department has increased focus on the condition of railroad bridges across the state,” and had not yet completed an assessment on the Rockland branch. “Early indications are that work will need to be done to support ongoing freight-rail operations,” it said.

Because of this, the board then proposed the three-weekend pilot in August of that year, according to the rail authority’s website, in order to “focus on what is anticipated to be the highest ridership demand period and recover operating costs through the fare box.”

Once the budget is completed, Quinn said the rail authority plans to restart a conversation about the service with Bruce Van Note, the new commissioner of the Department of Transportation, who she said has “expressed willingness to make use of the resource, but wants to make sure it is a fiscally responsible decision.”

Despite the setbacks and the list of items that still need to be accomplished, Quinn said she is “optimistic for next year.”

hlaclaire@timesrecord.com


Only subscribers are eligible to post comments. Please subscribe or login first for digital access. Here’s why.

Use the form below to reset your password. When you've submitted your account email, we will send an email with a reset code.