A partially completed tower and a finished tower are seen in a section of the NECEC corridor along Route 201 in Bingham in December 2022. Gregory Rec/Staff Photographer
The developer of a controversial 145-mile electricity transmission line through western Maine has told state regulators it’s making progress after resuming work last October, but projects such as setting foundations for poles and running wires are only about one-third completed.
In a report Monday on the New England Clean Energy Connect, Avangrid, the parent company of Central Maine Power, told the Public Utilities Commission that access to the route is about 81% complete. However, 294 foundations for the setting of poles have been completed, or about 41% of the total; 217 poles have been set, 31% complete; and 36 circuit miles of wire work are done, or 34% of what’s required, Avangrid said.
The corridor, which is to bring hydropower from Canada to the New England electrical grid, has grown to $1.5 billion from an original price tag of $1 billion due to delays and cost inflation.

The project is organized under NECEC Transmission LLC, a subsidiary of Connecticut-based Avangrid Inc., the parent company of Central Maine Power. Both are controlled by Iberdrola, a Spanish multinational energy company.
The transmission line will connect 1,200 megawatts to the New England electrical grid.
The state Department of Environmental Protection halted work on the corridor in November 2021 after voters killed the project in a referendum. In court battles that followed, NECEC’s backers said the project had established “vested rights” to continue construction. A Cumberland County jury decided in April 2023 that the project may resume.
Advocates said the project would help reduce greenhouse gas emissions. Opponents were skeptical of the environmental benefits and said developers would gouge a path for the transmission line through some of Maine’s most pristine forested areas.
The project was initially planned in 2018 to begin with tree clearing in January 2020 and have power flowing at the end of 2022. Construction of the transmission line started in January 2021 with right-of-way clearing and access road preparation followed by installation of steel structures the following month, Avangrid said.
Avangrid told Maine regulators all contracts that were in place before construction stopped in November 2021 have been renegotiated.
Contracts for construction and materials for the high voltage direct current transmission line and network upgrades were awarded and executed, including contracts with construction and clearing companies with a “strong presence in Maine,” it said. NECEC is giving preference to hiring Maine workers, it said.
In addition, steel poles and most of the transmission materials, such as conductor, fiber and insulators, have been received, Avangrid said.
The report provided no information about when the project may be completed but indicated another report would be filed in January. Avangrid also did not say how much the delay may have cost developers, and said it would not comment on the report.
State Public Advocate William Harwood said Avangrid should be able to provide at least a timeline for completion. The project may no longer be in public view since the highly publicized legal battles ended, he said Wednesday.
Before construction halted, 139 miles of the high-voltage direct current right-of-way was cleared, Avangrid said. In addition, workers had installed 107 pole bases and 78 poles. The line is entirely cleared of trees and hundreds more pole bases and poles have been installed and 178 poles have had wires installed.
In Lewiston, construction of an electric converter station resumed in August 2023. Since construction resumed the remaining site preparation work has been completed and building foundations have been completed.
Send questions/comments to the editors.
Join the Conversation
We believe it’s important to offer commenting on certain stories as a benefit to our readers. At its best, our comments sections can be a productive platform for readers to engage with our journalism, offer thoughts on coverage and issues, and drive conversation in a respectful, solutions-based way. It’s a form of open discourse that can be useful to our community, public officials, journalists and others. Read more...
We do not enable comments on everything — exceptions include most crime stories, and coverage involving personal tragedy or sensitive issues that invite personal attacks instead of thoughtful discussion.
For those stories that we do enable discussion, our system may hold up comments pending the approval of a moderator for several reasons, including possible violation of our guidelines. As the Maine Trust’s digital team reviews these comments, we ask for patience.
Comments are managed by our staff during regular business hours Monday through Friday and limited hours on Saturday and Sunday. Comments held for moderation outside of those hours may take longer to approve.
By joining the conversation, you are agreeing to our commenting policy and terms of use. More information is found on our FAQs.
You can modify your screen name here.
Show less
Join the Conversation
Please sign into your Sun Journal account to participate in conversations below. If you do not have an account, you can register or subscribe. Questions? Please see our FAQs.