WINDSOR (AP) — Central Maine Power is nearing completion of a $1.4 billion power grid upgrade.
Workers on Monday are going to set a 101-foot tall transmission structure, which represents the last major piece of the Maine Power Reliability Project.
Construction began in 2010 on the five-year project — the first major update of Maine’s power grid in more than 40 years.
The project has doubled the capacity of the grid’s backbone in Maine with a new 345,000-volt transmission line from Orrington to Eliot, near the New Hampshire border. Also included are five 345,000-volt substations. All told, there are 440 miles of new transmission lines.
Iberdrola paid for the improvements — about half with cash and half through borrowing. The money will be recouped from New England electric ratepayers.
Success. Please wait for the page to reload. If the page does not reload within 5 seconds, please refresh the page.
Enter your email and password to access comments.
Invalid username/password.
Please check your email to confirm and complete your registration.
Only subscribers are eligible to post comments. Please subscribe or login first for digital access. Here’s why.
Use the form below to reset your password. When you've submitted your account email, we will send an email with a reset code.
-
Portland Sea Dogs
Red Sox prospects in Portland are tearing up the basepaths
-
Track & Field
Track and field: Poland boys, girls finish third in Division 2 at WMC championships
-
Track & Field
Track and field: Brunswick sweeps KVAC Large School championships
-
Portland Sea Dogs
Sea Dogs, Fisher Cats split doubleheader at Hadlock Field
-
Varsity Maine
High school roundup: Monmouth uses big innings to top Dirigo in baseball